Netrokona University (Biswas Builders)

Project Highlight: Netrokona University Campus Client: Biswas BuildersLocation: Netrokona, BangladeshProject Type: University Campus FoundationTotal Piles: 1,200 NosEquipment Used: DTZ 420 Ton Hydraulic Static Pile Driving Machine Project Overview:AE Construction Ltd successfully completed the foundation piling work for the Netrokona University Campus, commissioned by Biswas Builders. The project involved the installation of 1,200 pre-cast concrete piles, […]
Kumudini Hospital Project (Sheltech)

Project Highlight: Student Hostel – Kumudini Hospital Client: Sheltech EngineeringLocation: Kumudini Hospital CampusProject Type: Student Hostel FoundationTotal Piles: 520 NosEquipment Used: Changhee 320 Ton Hydraulic Static Pile Driving Machine Project Overview:AE Construction Ltd was entrusted with the piling work for the Student Hostel project at Kumudini Hospital, a development led by Sheltech Engineering. The scope […]